Warning: file_exists(): open_basedir restriction in effect. File(../layoutv3/pre_render.php) is not within the allowed path(s): (/home/merittimes/.composer:/home/merittimes/web/merit-times.com/public_html:/home/merittimes/web/merit-times.com/private:/home/merittimes/web/merit-times.com/public_shtml:/home/merittimes/tmp:/tmp:/var/www/html:/bin:/usr/bin:/usr/local/bin:/usr/share:/opt) in /home/merittimes/web/merit-times.com/public_html/parent/_page.php on line 160

Warning: file_exists(): open_basedir restriction in effect. File(../layoutv3/render.php) is not within the allowed path(s): (/home/merittimes/.composer:/home/merittimes/web/merit-times.com/public_html:/home/merittimes/web/merit-times.com/private:/home/merittimes/web/merit-times.com/public_shtml:/home/merittimes/tmp:/tmp:/var/www/html:/bin:/usr/bin:/usr/local/bin:/usr/share:/opt) in /home/merittimes/web/merit-times.com/public_html/parent/_page.php on line 322
桃園鐵路地下化進展 台鐵中壢臨時前站6月16日啟用 | 人間福報

桃園鐵路地下化進展 台鐵中壢臨時前站6月16日啟用

THE MERIT TIMES
吳亭頤
字級
收藏文章
67觀看次
中壢臨時前站將於今年6月16日啟用。圖/鐵道局提供
中壢既有車站將辦理地下化工程。圖/鐵道局提供

【記者吳亭頤綜合報導】「桃園鐵路地下化計畫」於2020年9月奉行政院核定,原預計2029年4月完工,鐵道局今天說,中壢臨時前站新建工程將於今年6月16日啟用,同時地下化的永久站(CJ17標工程)亦將開始施作,但受缺工、缺料及延伸段影響將延後完工期程。

交通部鐵道局說明,「桃園鐵路地下化計畫」路線北起新北市鶯歌區鳳鳴陸橋南至桃園市平鎮區台66線,改建3座既有車站(桃園、內壢、中壢),新建5座通勤車站(鳳鳴、中路、桃園醫院、中原、平鎮),全長17.9公里,總建設經費約1048億元。

鐵道局說,中壢臨時前站新建工程將於6月16日啟用,地下化的永久站(CJ17標工程)也將同步開始施作,另外,鳳鳴臨時站預計今年底完工、平鎮臨時站預計2年後,但近年受缺工、缺料、工程經費、遺址還有平鎮延伸段影響,將再增加3至4年工期、600至700億元經費。

鐵道局指出,為維持鐵路正常營運,於極為有限之空間下,本計畫需辦理多次軌道切換,工序繁瑣費時,其中尤以新建中壢車站為桃地計畫中最具關鍵的指標項目,涉及台鐵、桃園捷運及機場捷運延伸線地下隧道施作順序及站體銜接作業。

鐵道局指出,為因應機場捷運延伸線地下隧道需通過既有中壢站及軌道區下方,施工期間必須維持既有鐵路營運及鐵路地下化工程之推動,故既有中壢前站必須遷移,以騰出空間供機場捷運及中壢地下車站依序施作。

鐵道局提到,中壢臨時前站工程主要內容包含車站大廳、機車停車場及臨時行李房等,並整合原有臨時後站跨站天橋,維持前後站的聯通,並同步啟用臨時月台,以提供隔日台鐵正常旅運服務。另為配合中壢臨時前站啟用,站前中和路及周遭道路將提前於6月上旬辦理改道,改為由西向東單向通行。

中壢臨時前站啟用後,既有中壢前站將由台鐵公司辦理設施設備搬遷,預計今年9月拆除中壢前站後即可騰出用地供中壢永久車站地下化站體施工。鐵道局指出,中壢車站地下化完工後,預計改為地下1層為穿堂、地下2層為台鐵月台、地下3層為捷運,地面上則有桃園市政府及台鐵共同開發的3棟大樓。