Warning: file_exists(): open_basedir restriction in effect. File(../layoutv3/pre_render.php) is not within the allowed path(s): (/home/merittimes/.composer:/home/merittimes/web/merit-times.com/public_html:/home/merittimes/web/merit-times.com/private:/home/merittimes/web/merit-times.com/public_shtml:/home/merittimes/tmp:/tmp:/var/www/html:/bin:/usr/bin:/usr/local/bin:/usr/share:/opt) in /home/merittimes/web/merit-times.com/public_html/parent/_page.php on line 160

Warning: file_exists(): open_basedir restriction in effect. File(../layoutv3/render.php) is not within the allowed path(s): (/home/merittimes/.composer:/home/merittimes/web/merit-times.com/public_html:/home/merittimes/web/merit-times.com/private:/home/merittimes/web/merit-times.com/public_shtml:/home/merittimes/tmp:/tmp:/var/www/html:/bin:/usr/bin:/usr/local/bin:/usr/share:/opt) in /home/merittimes/web/merit-times.com/public_html/parent/_page.php on line 322
高捷岡山車站6月完工 黃線預計10年後完成 | 人間福報

高捷岡山車站6月完工 黃線預計10年後完成

THE MERIT TIMES
字級
收藏文章
87觀看次
高雄捷運黃線。圖/高雄市捷運局提供

【本報高雄訊】高雄捷運四線齊發,建設工程如火如荼進行,包括岡山路竹延伸線第一階段、第二A階段、小港林園線、黃線。最快是岡山路竹延伸線第一階段包含捷運岡山車站,預計6月20日完工;最慢則是黃線,預計10年後完工。

有網友整理截至3月底公布的公共工程資料,岡山路竹延伸線第一階段(R24至RK1)工程進度已達97.18%,包含車站、軌道、道路復舊、跨站天橋、站前廣場等工程,預計6月20日完工,是高捷紅線北延重要的里程碑。

岡山路竹延伸線第二A階段由RK1(不含)至RK6段,包括岡山農工、本洲產業園區、高雄科學園區、高苑科技大學、南路竹等站(暫定名)。其中土建暨軌道統包工程進度7.13%,包括期末設計、BSS7主變電站、基樁作業等工程;機電系統統包工程進度32.76%,整體工程預計2028年12月21日完工,約4年半後。

小港林園線由R3小港站經沿海路至林園高值化產業園區(R3至RL7)土建工程及軌道工程標都已於去年完成簽約,目前只有機電系統(含能源調度中心)統包工程資訊,進度0.45%,預計2033年2月9日完工,近9年後。

捷運黃線目前僅有機電系統暨機廠與主變電站統包工程資訊,進度5.2%,預計2034年7月21日完工,約10年後。

另外YT01標軌道工程統包工程去年簽約、YC01標土建及設施機電統包工程去年簽約、YC03今年簽約,目前都在工程前設計階段;YC02標22日開資格標,共計一家投標,經審其資格符合招標文件規定,得參與後續評選。

後續在基本設計階段的有岡山路竹延伸線第二B階段,規畫中的有捷運紫線及前鎮漁港聯外軌道。網友表示,「10年後高雄又是不同景色」、「期待今年紫線也能有好消息」。