Warning: file_exists(): open_basedir restriction in effect. File(../layoutv3/pre_render.php) is not within the allowed path(s): (/home/merittimes/.composer:/home/merittimes/web/merit-times.com/public_html:/home/merittimes/web/merit-times.com/private:/home/merittimes/web/merit-times.com/public_shtml:/home/merittimes/tmp:/tmp:/var/www/html:/bin:/usr/bin:/usr/local/bin:/usr/share:/opt) in /home/merittimes/web/merit-times.com/public_html/parent/_page.php on line 160

Warning: file_exists(): open_basedir restriction in effect. File(../layoutv3/render.php) is not within the allowed path(s): (/home/merittimes/.composer:/home/merittimes/web/merit-times.com/public_html:/home/merittimes/web/merit-times.com/private:/home/merittimes/web/merit-times.com/public_shtml:/home/merittimes/tmp:/tmp:/var/www/html:/bin:/usr/bin:/usr/local/bin:/usr/share:/opt) in /home/merittimes/web/merit-times.com/public_html/parent/_page.php on line 322
公安過關 大巨蛋拚年底試營運 | 人間福報

公安過關 大巨蛋拚年底試營運

THE MERIT TIMES
本報台北訊
字級
收藏文章
23觀看次
【本報台北訊】台北市長蔣萬安昨日表示,台北大巨蛋一月九日正式拿到內政部所核發的防火避難與性能審查的核可函,接下來會要求遠雄按圖施工,希望四月就可以完工,並爭取七月能夠申請使用執照,年底進行試營運,目前初步希望在第一階段,先進行一萬人的場地試營運,接下來視後續整體狀況需求,再來進行開放。

前台北市長柯文哲任內通過消防審查,且遠雄也願意放棄國賠重新議約,但是內政部遲未發放關於公共安全的防火避難與性能審查認可函,蔣萬安競選期間大喊上任一年內完成大巨蛋營運,也因此備受關注。

對於大巨蛋使用執照變更部分,內政部表示,要由遠雄依照認可書內容,再向台北市政府申請變更。

蔣萬安說,北市府盡最大的力量,積極和中央溝通協調,從上任開始就和內政部進行相關溝通,就這個事情來了解討論,接下來還有很多需要跟中央一起合作的事項。他說,下周會和副市長李四川實際到大巨蛋了解內部狀況,希望透過實地了解,有更完整的規畫,希望能夠都按照計畫進行。

李四川昨日下午臨時新增行程,視察公共安全聯合稽查作業,並接受媒體訪問。就內政部對大巨蛋的防火避難性能審查通過,並發下認可函一事,他表示,他要先代表台北市長蔣萬安表達對內政部的感謝,就職以來內政部給予了很多指導。

試營運先放行萬人 逐步開放

李四川指出,他日前也到大巨蛋巡視,要求遠雄能夠配合,並盡速報給內政部,使內政部發放認可允許函;接下來會做執照變更審查,假如能在農曆過年前完成,遠雄就會進行約二至三個月的施工,今年四月應能將工程全部完成,目標七月取得使用執照、年底試營運。

外界對於一次疏散五萬人有所疑慮部分,李四川說,試營運不會一次進這麼多人,希望第一次試營運時採一萬人入場,讓其適應,就類似已完工啟用的小巨蛋一樣,逐步按照人流進行開放。

李四川表示,至於大巨蛋其他內部工程及招商部分,看起來應是進行順利,有機會下周邀請市長蔣萬安到大巨蛋基地現場巡查,一定會嚴格要求及督導大巨蛋,至於相關BOT部分,應由遠雄負責。