Warning: file_exists(): open_basedir restriction in effect. File(../layoutv3/pre_render.php) is not within the allowed path(s): (/home/merittimes/.composer:/home/merittimes/web/merit-times.com/public_html:/home/merittimes/web/merit-times.com/private:/home/merittimes/web/merit-times.com/public_shtml:/home/merittimes/tmp:/tmp:/var/www/html:/bin:/usr/bin:/usr/local/bin:/usr/share:/opt) in /home/merittimes/web/merit-times.com/public_html/parent/_page.php on line 160

Warning: file_exists(): open_basedir restriction in effect. File(../layoutv3/render.php) is not within the allowed path(s): (/home/merittimes/.composer:/home/merittimes/web/merit-times.com/public_html:/home/merittimes/web/merit-times.com/private:/home/merittimes/web/merit-times.com/public_shtml:/home/merittimes/tmp:/tmp:/var/www/html:/bin:/usr/bin:/usr/local/bin:/usr/share:/opt) in /home/merittimes/web/merit-times.com/public_html/parent/_page.php on line 322
蔣萬安任內首條通車段 北捷最難工程 東延段後年完工 | 人間福報

蔣萬安任內首條通車段 北捷最難工程 東延段後年完工

THE MERIT TIMES
本報台北訊
字級
收藏文章
26觀看次
【本報台北訊】台北捷運信義線東延段遭遇捷運工程史上最困難的複雜地質,預定今年底完成的工期嚴重延宕近2年。市長蔣萬安昨天表示,已陸續克服工程挑戰,未來通車可連接東環段,緩解內科交通,讓北捷路網更完整。

捷運東延段被稱為北捷史上最困難工程,包括站體開挖是一般車站2倍大,還有向下開挖深10層樓,更行經台北市邊陲丘陵四獸山的山麓,地質條件複雜。東延段原本預定今年底完工,如今要延到2025年底,完工後通過初履勘即可營運,將是蔣萬安任內第1條通車的捷運。

台北市捷運工程局表示,東延段工程已全面進入站體結構施工高峰期,正在進行第3、4條潛盾隧道掘進作業,今年3月底完成隧道1325公尺,進度約70.4%,儘管目前工程進度有點落後,但後續工程狀況已經在掌控中。

蔣萬安表示,台北市整體捷運路線長152公里、共131個車站,儘管東延段路線不長,僅1.4公里,但代表的意義卻相當重大。施工過程因地質複雜,開挖機具都陷入泥淖,但克服工程困難後,未來東延段通車,不僅連接東西向交通,民眾到虎山踏青、信義行政中心洽公都可以搭乘。